Pilot Study at Former Gasworks, Southeast England, UK


PetroCleanze and ORC Advanced used to Reduce Mass Loading Onsite

Summary

REGENESIS have recently been involved in a remedial pilot study for a former gas works site in the South East, as part of its proposed high density development scheme. The site is situated within a high risk area for groundwater vulnerability with an aquitard protecting the underlying principal aquifer. A reduction in DNAPL and groundwater LNAPL concentrations are required to allow deep piling to take place.

icon-pdf Pilot Study at Former Gasworks, Southeast England, UKDownload the pdf

PS_REG_1606_KrM48835_PetroH_PAH_PetroC_ORC_UK Pilot Study at Former Gasworks, Southeast England, UK

Treatment

Multiple PetroCleanze applications were used to desorb soil-bound TPH and PAH contamination including DNAPL. This was then removed using a pump and treat system, rapidly reducing the contaminant mass in the target area. This will then allow piling works to occur, reducing the risk that this will drive contamination down into the deep bedrock aquifer below.

ORC Advanced was then applied in order to degrade residual groundwater contamination in the area. The ORC Advanced will also mitigate against residual contamination entering the shallow aquifer through disturbance during piling.

What’s Special?

  • The pilot showed that within 10 weeks, significant mass reduction could be achieved
  • A number of dosages, pumps, spacing and abstraction rates were tried during the pilot in oder to discover the most effective treatment
  • The pilot study is scalable to the entire site
  • Targeted remediation to reduce the contaminant mass in the most sensitive areas has the potential to dramatically reduce remediation costs for the developer