- Regulatory standards met following single injection of PlumeStop
- Remedial injection event completed in two days with the first clean samples obtained within three weeks post-injection
- Effective design and approach led to time and cost savings for the client
A former gasoline retail station located in Whitby, Ontario, was the site of BTEX and PHC contaminants requiring remediation. Excavation, as well as pump and treat approaches, had been used to address contaminant levels, but groundwater remained impacted by BTEX and PHC F1 and F2 above regulatory standards. While the contractors were able to remove the majority of impacts, they were not able to remediate the site to the applicable regulatory standards.
The client hired INSITU Remediation Services LTD (IRSL), an environmental firm specializing in in situ remediation technologies, to reduce the levels and reach required standards safely and effectively following a tendered contract issued to a total of five contractors. IRSL was chosen based on their innovative approach and lower total cost. Using a proprietary design, IRSL injected PlumeStop Liquid Activated Carbon™, to remediate residual BTEX and PHC F1 and F2 groundwater impacts.